MAY 08 2023

NORTHERN ROAD AXIS OF CRETE (BOAK)

Our company submitted a binding offer for the BOAK project (Northern Road Axis of Crete) of the Ministry of Infrastructure & Transport.

The Chania-Heraklion section of BOAK is 157.5 km long and is currently the largest active concession tender.

A very important aspect of the project is that the construction of 34 km tunnels is foreseen for both traffic streams.

The technical characteristics of the Chania – Heraklion section are as follows:

  • Motorway length: 157.5 km.
  • 2 traffic lanes per direction with emergency lane (ELA).
  • 26 tunnels.
  • 10.80 km of new bridges, 23 of which exceed 100 meters in length.
  • 20 new grade interchanges and upgrading of the existing 18 grade interchanges in the bypass roads of Chania, Rethymno, Heraklion.

 

The announcement of the provisional contractor is anticipated.

Participation: MYTILINEOS S.A (M CONCESSIONS) - AKTOR CONCESSIONS

11/29/2024
Epirus Streetlighting

Contract signature for the project «Upgrade of the streetlighting system in Epirus road network», through a PPP scheme with Epirus Prefecture.

Read More
11/18/2024
Minagiotiko Dam (1)

Our company was provisionally awarded the project «Design, Construction, Financing, Operation and Maintenance of the Minagiotiko Dam», through a Public Private Partnership (PPP) with the Ministry of Agriculture.

Read More